EAST BRANDYWINE TOWNSHIP PLANNING COMMISSION

REGULAR SESSION

Wednesday, August 4, 2004 - 7:30 PM

 

Those in Attendance:

Mr. Bruce Rawlings , Chairman

Mr. Stephen Cushman, Vice-Chairman

Mr. Charles Giordano , Member

Mrs. Sandra E. Moser, Member

Mr. Mervin Thomas, Member

Mr. Scott T. Piersol , Township Manager

Mr. Albert Giannantonio, Township Engineer

Mrs. Mary Beth Smedley, Township Secretary/Treasurer

 

Absent:

Mr. Michael Corbin , Member

Mrs. Deborah Marshman, Member

Mrs. Beth Valocchi, Ex Officio Member

 

Planning Commission Meeting Minutes – July 7, 2004

 

Mr. Rawlings asked if there were additions or corrections to the above minutes.  There were none.  Mrs. Moser then made a motion to approve the above Minutes as submitted.  Mr. Cushman seconded the motion, with all voting Aye. 

 

Scott Zoning Hearing – September 2, 2004

 

The Zoning Hearing Board of East Brandywine Township will meet on Thursday, September 2, 2004 to conduct a public hearing on the application of Gary and Noreen Scott to install a swimming pool at their residence located at 129 Waring Drive in the Keats Glen Subdivision.  The property is located in the I/R Zoning District.  The proposed swimming pool will not comply with the minimum 25 foot setback from the rear property line as required in Section 399-75.E of the Zoning Ordinance.

 

Mr. Scott explained that the proposed swimming pool does not meet the required rear yard setbacks.  The plan shows the swimming pool 18 feet from the rear property line.  The rear of the property backs up to common open space that contains woodlands and a   detention basin.  To the left of the property is farm field, and to the right is the Warmhold  residence.  Mr. Scott provided a copy of a letter dated July 29, 2004 from Mr. Warmhold stating that he has no opposition to construction of the swimming pool. 

 

One reason that Mr. and Mrs. Scott chose this location for the pool is because it is approximately 10 feet away from an existing deck.  A representative from the pool   company has suggested it would be a safety issue to have the pool placed closer to the deck since a person could feasibly jump from the deck into the pool.  The property slopes away from the Warmhold property so there should be no grading problems.  Mrs. Moser remains concerned about granting these types of variances.  She was particularly concerned about noise from the filter.  Mr. Scott stated the filter would be placed to the left of the pool, away from the Warmhold residence.  Mr. Rawlings suggested the applicant consider other locations for the pool prior to the Zoning Hearing to see if they could diminish or eliminate the need for the variance.

 

After review of the plan, Mr. Cushman made a motion to recommend that the Planning Commission take no position on this application.  Mr. Thomas seconded the motion with all voting Aye. 

 

 Echo Dell Builders

     

The owners and applicants of the subdivision are Echo Dell Builders, Inc. and James A. and Jeanette B. Crouthamel.  The project site is located on the east side of Echo Dell Road between Pancoast Lane and Hopewell Road and is in the R-1 Residential District. The site currently consists of three existing properties, Parcels 30-02-86.29, 30-02-101.0 and 30-02-101.1.  Echo Dell Builders, Inc. currently own parcels 86.29 and 101.1 and Mr. and Mrs. Crouthamel own parcel 101.  The total combined property area is 11.798 acres.  The Crouthamel property contains an existing 2-story dwelling, driveway, well, and on-site septic system.  The paved driveway has access from Echo Dell Road , which has a 50-foot access and utility easement over the adjacent White property.  Echo Dell Builders, Inc. properties contains an existing 2 story dwelling, driveway, well, on-site septic system and pond area.  The driveway has a 50-foot access easement over the Crouthamel property and connects with the drive to their lot. 

 

The plan proposes to combine the three parcels and re-subdivide the property into 4 lots.  Lot #1 will be 2.485 acres and will retain the existing Crouthamel dwelling and utilities and maintain its existing acreage with no new construction proposed.  A portion of the connecting stone driveway is to be removed.  A new driveway is proposed for access to the remaining Lots #2, 3 and 4.  Lots #2 and #3 will be 2.473 acres and 3.969 acres respectively, and contain a new dwelling, well, on-site septic system and underground seepage bed on each.  Lot #2 will contain the existing septic disposal area and a replacement septic area easement for Lot #1.  Lot #3 will contain the existing pond as a drainage easement.  Lot #4 will be 2.871 acres in size and will retain the existing Echo Dell dwelling and utilities with no new construction proposed. 

 

Mr. Joseph Mastronardo, engineer for the applicant, discussed the revised preliminary plan.

 

20.    The applicant has received a letter of adequacy from the Chester County Conservation District and approval of the NPDES Permit.

 

26.              a. The sewage facilities planning module has been approved by the Chester County Health Department.

 

26.              b. The Planning Commission agreed that the landscaping plan was adequate.  Mr. Rawlings did ask that Norway Spruce be used instead of White Pines.  The applicant agreed to this. 

 

26.              c. The applicant has agreed to provide orange construction fencing to define the limits of tree clearing and protection.  The detail and location of the fencing protection will be provided on the final plan.

 

19.    Section 350-49.A – The utility trench detail will be shown on the final plan.

 

Waiver Request

 

The applicant requested a waiver of payment of the traffic impact fees associated with this development.  Mr. Mastronardo stated the subdivision only involved the creation of two additional lots, and there are no new roadways or extension of existing roadways planned in conjunction with this plan.  The Planning Commission felt that each additional lot does affect traffic in the community and to recommend this waiver would be setting a precedent.  After review of the request, Mr. Cushman made a recommendation that the Board of Supervisors deny this waiver request.  Mr. Thomas seconded the motion, with all voting Aye.

 

Preliminary Plan Approval

 

Mr. Cushman made a recommendation that the Board of Supervisors grant preliminary plan approval for this subdivision with the condition that the applicant satisfies all of the items outlined in the Yerkes review letter of July 20, 2004 , and in these minutes.  Mr. Rawlings seconded the motion, with all voting Aye.

 

 Decovny Subdivision

 

The plans depict a proposed 26 lot subdivision of an existing 89.211 acre parcel (tax map parcel 30-6-20) located on the north side of Dowlin Forge Road.  The parcel contains an existing farmhouse and farmstead buildings, wooded steep slopes, ponds, wetlands, and a tributary stream to the East Branch of the Brandywine Creek.  The parcel is situated within the R-1 Zoning District and each lot is to be served by on-site water supply and sewage disposal.  Mr. Greg Balbirnie from Robert Bruce Homes and Mr. Adam Brower, engineer for the project, discussed the road layout.

 

At the last Planning Commission meeting, it was suggested that the applicant consider moving Road A farther south on the property.  This may result in the loss of Lot 15 or require reorientation of some lot lines, but would also eliminate the 640 foot long segment that contains a centerline grade of 9.5%.  Section 350-34.B. of the Ordinance states centerline grades shall not exceed 7 percent, except that a maximum grade of 10 percent may be permitted for short lengths where natural contours provide conditions for minimal grading at the steeper grade.  The Planning Commission does not consider 640 feet a short length.  The Ordinance Task Force has recommended 300 feet as a short length and in fact, the Zoning Ordinance is proposed to be revised to reflect that number.

 

Mr. Brower discussed the benefits of the road layout that was presented at the last Planning Commission Meeting.  He stated that shifting the road to the south would result in more grading and disturbance of the area.  In addition, the road would be placed very near wetlands, may impact some of the large trees in the area, and could create a danger of de-watering the area.  Mr. Thomas asked Mr. Brower to review the grading throughout the road system in the development.  There are other areas where the centerline grade exceeds 9%, for short distances. 

 

The Planning Commission is concerned that 640 feet at 9 ½ % may cause problems with snow plowing, access for emergency vehicles and safety issues for residents and visitors within the development.  Mr. Brower stated there were other roads in the Township that   had similar grades to the one he is proposing.  In addition, he stated that overall grades exceeding 9% is a small percentage of the entire road.  Mr. Cushman suggested that Mr. Brower may want to look at the percentage and provide this information to the Planning Commission for their review.   

 

In order for the Planning Commission to give an opinion, Mr. Brower was asked to provide a plan for the road layout suggested at the last Planning Commission meeting. Mr. Giannantonio stated that unless the applicant provided the alternative road layout there was no measurable way to determine if shifting the location of the road would cause more grading and disturbance, or would impact the wetlands.  Mr. Giannantonio went on to say that if the preferred road layout was the original design, snow and ice problems would be lessened because the road has a south facing slope.  Mr. Brower will provide additional information on the alternate layout for discussion at the next Planning Commission Meeting.   

           

Decovny - Extension

 

Mrs. Smedley reported that the applicant is providing an extension for the Planning Commission to review their application until September 18, 2004 .  Mr. Rawlings made a recommendation that the Board of Supervisors accept this extension.  Mr. Thomas seconded the motion, with all voting Aye. 

 

AWI Croppers – Extension

 

Mrs. Smedley reported that the applicant is providing an extension for the Planning Commission to review their application until October 21, 2004 .  Mr. Rawlings made a recommendation that the Board of Supervisors accept this extension.  Mrs. Moser seconded the motion, with all voting Aye. 

Brandywine Wallace Elementary School

 

Last Friday, Mrs. Smedley was informed by Planning Commission member Beth Valocchi that the School District is taking the position that the Brandywine-Wallace Elementary   School land development plan was complete, and the 90-day clock for land development plan review was running. Mrs. Smedley contacted Guy Donatelli of Lamb, Windle & McErlane last Friday to discuss this issue.

 

The Township’s position is that the submission was incomplete, since submissions for the Chester County Soil and Conservation District NPDES permit, and the PA DEP Sewage Facilities Planning Module, were not provided with the original plan submission, provided to this Office on June 14, 2004 . This fact has been acknowledged as recently as Friday, July 30, 2004 by Michael Dirks of Chester Valley Engineers, Inc., in a discussion with Mrs. Smedley.

 

Mr. Piersol and Mr. Gil Lappano, Facilities Director of the School District discussed this issue prior to the submission of the land development plan. They agreed the Township would accept a partial plan submission, and begin reviews only on the portions submitted, and that the review time clock would not begin until such time as the remaining items were received by East Brandywine Township for distribution.

 

Mr. Piersol sent a letter in regard to the above discussion, to Mr. Lappano, and enclosed an excerpt from the Township Land Use Code, Subdivision and Land Development, which applies to this situation. Subsection 350-13 C states: “The application shall not be    deemed to be submitted until a complete application and the required fees and the required escrow deposit all have been submitted.” Subsection 350-13 D requires copies of the plan be submitted to the Chester County Health Department and the Chester County Conservation District.

 

  East Brandywine Township accepted this incomplete application with the understanding that plan reviews would be initiated on the items submitted. Acceptance of a partial submission would expedite the review process for this land development plan

 

In his letter, Mr. Piersol stated that, should the School District insist that a complete submission was received by the Township on June 14, 2004, and the 90-day time clock for plan review was started, the Board of Supervisors will exercise its option to deny the plan, due to an incomplete plan submission, as provided by Section 350-14 B (3) of the Township Land Use Code.  Based on this section, the Township would have until October 13, 2004 to render a decision.

 

Mr. Piersol requested a letter from the School District, their engineering firm, or their Solicitor acknowledging the submission of an incomplete land development plan for this project, agreeing that the 90-day time clock for plan review has not started due to the    incomplete land development plan submission, and requesting the Township continue its plan review upon receipt of a revised plan set, prior to the Board of Supervisors’ public meeting on Wednesday, August 18, 2004.

Trail Easement Connection to HeatherWynd Development

 

At the July 7th Planning Commission meeting, Momemee Associates showed an illustrative site plan, which included a trail interconnection to the Hopewell subdivision property line.  The plan also showed a portion of the adjoining Hopewell development along Tarrytown Lane , and what appeared to be a trail located behind some of the homes. Mr. Piersol investigated and found that the trail does not exist.

 

Since the Township has been encouraging the creation of these passive recreation facilities within new developments, the Planning Commission asked Mr. Piersol to    inquire if such a trail interconnection between the Hopewell development and the proposed HeatherWynd development could be discussed with the Hopewell Homeowners Association. 

 

Mr. Piersol contacted Mr. Stephen Gallo from Rouse/Chamberlin Homes and asked him to discuss this proposal with the Homeowners Association.  Mr. Gallo did so and reported that the Homeowners Association was not interested in permitting a trail interconnection.  They did not see the trail as a benefit to their community, only to residents in the HeatherWynd   Development.

 

The Planning Commission suggested that Mr. Piersol and Mr. Rawlings meet with members of the Homeowners Association to discuss the benefits to their development, and to the community as a whole.  The Township has a plan to create a trail “spine” to eventually link our parks with the Struble Trail.  Interconnection with other developments is part of our master plan.  Mrs. Smedley will contact Mr. Gallo to make these   arrangements. 

               

Ordinance Task Force

 

Mr. Piersol reported that the Township has received reviews from the Chester County   Planning Commission on two Vision Partnership Program Grant applications.  The reviews will be discussed at the August 25, 2004 Ordinance Task Force Meeting.   

 